Orientation Park Budget
Donations happily accepted! To sponsor one or more Orientation Park elements, or make a general donation, go to "Get Involved"
Park Elements Cost Status
Phase I
specimen rock: transport and placement $2715 completed 'mazama' sign on rock 1000
additional landscape rocks 500 completed
five statement trees 6 to 8 feet @ $550 each* 2750
general landscaping/surfacing* 5800
top soil* 600
wood chip mulch* 200
40 1 gallon plants * 320
grass and wildflower plugs (100)* 350
native grass and wildflower seed* 45
rock scree mulch* 50
irrigation* 250
tax * 870
*Plantas (Camden Shaw) total estimate: 11,235
Phase I: budget total $15,450
total contributions received: 3/15/22 $6100 Kick start funds have been provided
total contributions received: 7/26/22 $8345 through donations by several members
total contributions received: 9/15/22 $13345 of the Shaping Mazama stakeholder
group, and individual community
members.
total funds spent $3215
remaining Phase I available funds $2885
Phase II
widen and surface entry road $5000
benches 3 @ $500 each 1500
kiosk frame 6000
kiosk panels 4000
signs - pole 3 @ $500 each 1500
signs - small walkway 4 @ $100 each 400
signs - pedestrian crossing - 2 @ $100 each 200
plaza pavers (based on pit toilet status) 8000
Phase II: budget total $26,600
Phase I & II Admin (printing/website) $ 250
grand total - all phases $42,300